Danan Oil field development Project
Subject of the project: Danan oil field Development Project
Project location: Danan and Dehlran region in Ilam province
Client: ICOFC
Contractor: MAPNA Group Company
Project Management Services: Mapna Oil and Gas Development Company
Type of contract: EPC-EPD
Project Duration: 58 months according to the final addendum
Contractors/Manufacturers/Engineering consultants within Mapna Group: Mapna Noor Kish Drilling Company / Nasb Niroo Company / MECO Company/Tehran Energy Consulting Engineers/MONENCO Consulting Engineers
DANAN Sub-Surface Facilities Scope of Works for 11 new wells
Engineering, Procurement and Drilling/Drilling Services 11 new vertical wells.
Geophysics Scope of Works Description
Management, Design, Acquisition, Processing and Interpretation of Danan Oil Field Project.
DANAN Surface Facilities Scope of Work
Ø Engineering, Procurement, Construction and Commissioning of 11 New well locations, related access roads, fire lines, helipads, etc.
Ø Engineering, Procurement, Construction and Pre-commissioning, Commissioning, start-up and Performance tests of Wellhead Facilities for 11 new wells including (WHCP, CIP Packages and…)
Ø Engineering, Procurement and Erection of 2 Chemical Injection Packages for each Well as Skid Mounted
Ø Surveying, Routing, Design, Procurement and Construction of 6-inch flowline related to 11 new wells from the well locations to New Danan Manifold of around 55 kilometers length.
Ø Surveying, Routing, Engineering and Construction of access roads to the location of 11 new wells
Ø Engineering, Procurement, Construction and Pre-commissioning, Commissioning, start-up and Performance tests of all necessary equipment for the development of Danan Manifold for 11 New wells
Ø Surveying, Routing, Design, Procurement and Construction of the power overhead line network up to the location of 11 new wells.
Dehloran Surface Facilities Scope of Work
Dehleran Production unit is located in 20 kilometers southwest of Dehleran city at Ilam province, which has a Nominal capacity of 55,000 barrels per day of oil produced from Dehleran and Danan fields after processing and sweetening through a 16-inch-long pipeline. Stabilized Oil is pumped to about 52 km to Cheshme Khosh Desalination unit.
This Project Development, includes Engineering, Procurement, Construction and Pre-commissioning, Commissioning, start-up and Performance tests of a 10,000 barrels per day Desalting Package along with all related equipment (booster pump, heater, control system, etc.) and 10,000 barrels per day will be added to the Existing Capacity.
New DANAN Manifold
Wellhead facilities
New Flowlines and Access Road to New DANAN Wells
دیدگاهها بسته شدهاند.
آدرس: تهران، چهارراه جهان کودک ، ابتدای آفریقا شمالی، پلاک 43 شرکت توسعه نفت و گاز مپنا
ایمیل: info@mapnaogdc.com
© کلیه حقوق این تارنما متعلق به شرکت توسعه نفت و گاز مپنا میباشد.
کارشناس فروش و مشاوره
زمان پشتیبانی 9 تا 18 است
کارشناس فروش و مشاوره
زمان پشتیبانی 9 تا 18 است
کارشناس فروش و مشاوره
پیام خود را ارسال کنید