Parsi & Paranj Oil Field Summary
Location of the project: Ahvaz
Client: National Iranian South Oil Company
Contractor: Mapna Oil and Gas Development Company
Type of contract: NISOC IPC
Project period: 10 years with the possibility of increasing to 20 years
Contract effective date: Not effective yet.
The purpose of this project is to increase the production Daily Rate of Parsi and Paranj Oil fields with the Goal of increasing oil production by 33000 barrels from the current 46000 barrels up to 79000 barrels per day.
Paranj Oil Field Location
Parsi Oil Field Location
Paranj Oil Field is located 115 km southeast of Ahvaz. This field is located in the west of the Parsi Oil Field and in the northeast of the Karanj Oil field. From the 11 wells in this field, 10 are Production Wells and 1 is for Gas Injection.
Parsi Oil Field is located 120 km southeast of Ahvaz. It has 89 wells in Asmari Bangistan Reservoirs, of which 37 are
currently production wells.
Sub-Surface Scope of Work
Parsi Surface Scope of Work
Engineering, Procurement and Drilling/Drilling Services of wells As per below Table:
Oil |
New well |
Workover |
Disposal |
Gas Lift |
ESP |
Hydraulic |
Parsi |
15 |
5 |
2 |
15 |
15 |
1 |
Paranj |
11 |
3 |
1 |
15 |
|
1 |
Sum |
26 |
8 |
3 |
30 |
15 |
2 |
Ø Performing of FEED studies and preparing work packages for Surface EPC tenders
Ø Parsi Production Unit (CTEP) with a capacity of 85,000 barrels per day
Ø Desalting production Unit with a capacity of 65,000 barrels per day in the new Production unit (CTEP) in Parsi
Ø Skid Mounted Desalination Unit with a capacity of 20,000 barrels per day in the vicinity of Karanj exploitation unit.
Ø Wellhead Facilities and Flowlines for 29 wells in Parsi and Paranj Fields
Ø Control and Measuring equipment (Metering)
Ø Unit CS-100 compressor station with a capacity of 58 million cubic feet of gas
Ø unit CS-400 compressor station with a capacity of 72 million cubic feet of gas
Ø Water Treatment Unit with a capacity of 6000 barrels of water per day
Ø Performing Engineering and Existing facilities Optimization of Parsi and Paranj Fields
A part of the oil produced in the Parsi field and all productions of Paranj Oil field are sent to the Cluster unit through surface Facilities and flowlines, and a separation stage is performed in this unit. Subsequently, In the Karanj CTEP Unit, further separation is performed in the 2nd and 3rd stages as well as desalination.
In Darreh-Ney, three stages of Separation are done completely and after Metering the Product, the produced oil is pumped and exported the Karanj Unit for Desalination.
In addition to Drilling new wells, it is planned to update some facilities, increase Production, Recovery Operations and wells Workover, Construction of a Central Processing Unit and transfer produced oil for the independence of these Fields from the units located in Karanj.
Parsi field has 89 wells in Asmari and Bangestan reservoirs, of which only 37 wells have been introduced are in Production Mode according to MDP. The current rate of oil production in the Parsi cluster unit is about 23 thousand barrels per day from its 23 active wells. The production share of Parenj Field is 11,000 Barrels per day from its 6 active wells. The rate of oil production from Darreh-Ney unit is 12 thousand Barrels per day from 11 active wells.
Karanj Desalination Unit
Parsi Cluster-Manifold & Separation Area
C-400 Gas Compressor Station
دیدگاهها بسته شدهاند.
آدرس: تهران، چهارراه جهان کودک ، ابتدای آفریقا شمالی، پلاک 43 شرکت توسعه نفت و گاز مپنا
ایمیل: info@mapnaogdc.com
© کلیه حقوق این تارنما متعلق به شرکت توسعه نفت و گاز مپنا میباشد.
کارشناس فروش و مشاوره
زمان پشتیبانی 9 تا 18 است
کارشناس فروش و مشاوره
زمان پشتیبانی 9 تا 18 است
کارشناس فروش و مشاوره
پیام خود را ارسال کنید